Adani Energy Solutions won a Bihar transmission project to evacuate 2,400 MW from Adani Power's planned Pirpainti plant.

Orders · 19 Nov 2026 · Adani Energy Solutions (ADANIENSOL)

Adani Energy Solutions wins a ₹500 Cr order

The project adds 881 circuit km of lines and 3,160 MVA of substation capacity, with an estimated annual tariff of Rs 500 crore once commissioned.

Annual tariff (approx.): ₹500 Cr; Transmission capex (approx.): ₹91,500 Cr; Power evacuation capacity: 2,400 MW; Transmission lines added: 881 ckm.

NSE filing (PDF) · Company page

Anand Ganapathy K | SEBI Registered Research Analyst | INH000016630.